Home / Trades / Concrete

How to price and write concrete estimates and invoices

Concrete jobs are priced by square foot and thickness, with extra for excavation, reinforcement and finish. Itemizing prep and pour shows the customer why thicker or decorative slabs cost more.

How are concrete jobs usually priced?

Concrete work is priced by area and thickness. Contractors calculate the volume in cubic yards, add a waste allowance, then add excavation, base material, forms, reinforcement, finishing labor and any pump truck. Decorative finishes such as stamping cost more per square foot than a broom finish.

Access matters: if the truck can't reach the pour, pumping or wheelbarrowing changes the price significantly.

If you price from drawings, measure slab areas and footing lengths on the PDF first with the free PDF takeoff tool; the totals drop straight into an estimate.

What should concrete estimates and invoices include?

  • Square footage and slab thickness
  • Excavation, base material and compaction
  • Reinforcement: rebar, wire mesh or fiber
  • Finish type (broom, stamped, exposed aggregate)
  • Curing time and when the surface can be used

What are typical concrete line items?

Sample prices for illustration only.

Line itemQtyRateAmount
Excavation and grading
1 job × $900.00
1 job$900.00$900.00
Gravel base, compacted
6 yd × $55.00
6 yd$55.00$330.00
Rebar / wire mesh
600 sq ft × $0.80
600 sq ft$0.80$480.00
4" concrete slab, poured and finished
600 sq ft × $8.50
600 sq ft$8.50$5,100.00
Broom finish and control joints
1 ea × $0.00
1 ea$0.00$0.00

Which concrete template should you use?

Concrete Estimate Template

An estimate is a written, approximate price for a job, given before the work starts.

Concrete Invoice Template

An invoice is a request for payment for work that has been done or goods that have been delivered.

Concrete Bid Proposal Template

A bid is a firm price submitted to win a job, often against other contractors.

Concrete Quote Template

A quote is a fixed price offer for a defined piece of work.

Frequently asked questions

How do I estimate a concrete slab?

Calculate the volume (length × width × thickness ÷ 27 for cubic yards), add 5–10% for waste, then add excavation, base, reinforcement, forming, finishing labor and any pump truck fees.

Sources

  1. 811 Before You Dig — Common Ground Alliance. Call or request a locate through 811 a few days before any digging so underground utilities are marked.